- The role of Councilkeyboard_arrow_down
- Executive management
- Our elected memberskeyboard_arrow_down
- Meetingskeyboard_arrow_down
- Documentskeyboard_arrow_down
- Wellington Region reorganisation
-
Planningkeyboard_arrow_up
- Annual and Long-term Plans
- Local outcomes
- Building
- Operative District Plan 1999
-
Proposed District Plan (PDP)
- District plan review process
- Proposed District Plan – Appeals Version 2018
- Decisions Version 2017 – PDP
- Proposed District Plan Hearings 2016/17
- Urban Tree Variation Background
- Review Timeline
- PDP 2012
- Coastal Hazards
- Natural Hazards
- PDP Technical Reports
- Frequently asked questions
- Independent Review on PDP
- Variation 2
- Variation 3
- Variations 4 (A–H)
- Resource consents
- Submissions we have made
- Sustainability
- Projectskeyboard_arrow_down
- Job vacancieskeyboard_arrow_down
- Caring for the environment
- CarbonReduce/CEMARS certification
- Partnerskeyboard_arrow_down
- Local electionskeyboard_arrow_down
- Official Information Requests
District Plan review timeline
The following timeline gives an indication of dates for the District Plan Review process.
2012 |
|
|
29 November |
District Plan notified. |
|
29 November - 1 March 2013 |
General submission period. |
|
29 November - 2 April 2013 |
Coastal environment submission period. |
|
2013 |
|
|
April - September |
Submissions summarised.Submissions notified for further submissions (in support/opposition). |
|
June - December |
Pre-hearing meetings with submitters and/or experts. |
|
November |
Independent review of Proposed District Plan commissioned. |
|
2014 |
|
|
2 April |
Draft report on Independent Review of Kāpiti Coast Proposed District Plan released. |
|
24 June |
Final report on Independent Review of Kāpiti Coast Proposed District Plan received by council. |
|
24 July |
Council decides on Option 4 of Independent Review. |
|
August 2014 - May 2015 |
Redraft PDP provisions and maps (excluding coastal hazards) for submitter engagement. |
|
2015 - 2016 |
|
|
June 2015 - November 2015 |
Submitter engagement phase. |
|
August 2015 - February 2016 |
Pre-hearings and Facilitated Meetings as Required |
|
December 2015 onwards |
Draft S42A and S32 reports prepared in line with Hearing schedules. |
|
April - October |
Hearings and decisions. |