- The role of Councilkeyboard_arrow_down
- Executive management
- Our elected memberskeyboard_arrow_down
- Meetingskeyboard_arrow_down
- Documentskeyboard_arrow_down
- Wellington Region reorganisation
- Planningkeyboard_arrow_down
-
Projectskeyboard_arrow_up
- Kāpiti Gateway Centre
- Three Waters Reform Programme
- Raumati Village roading
- Te Moana Road safety
- Ōtaki Gorge Road slip
- Ōtaki Civic Theatre refurbishment
- Paraparaumu District Memorial Hall
- Kāpiti Expressway
- Paekākāriki seawall
- Making SH1 a local road
- Improving our town centres
- Elevate Ōtaki
- Energise Ōtaki
- Water meter project
- The Kāpiti Destination Management plan
- Job vacancieskeyboard_arrow_down
- Caring for the environment
- CarbonReduce/CEMARS certification
- Partnerskeyboard_arrow_down
- Local electionskeyboard_arrow_down
- Official Information Requests
Town Centres and Connectors Transformation | Project Timeline
This timeline outlines key milestones for our town centres improvements.
Month | Activity | Status |
July 2019–February 2020 | Shared pathway on Kāpiti Road |
Completed |
January–September 1019 |
Completed |
|
July–November 2018 |
Concept designs and planning for Mahara Place improvements |
Completed |
Late 2018 |
Rimu Road improvements. Safety improvements to the existing pedestrian crossing and cycle lane markings |
Completed |
April–July 2018 |
Creation of the first stage of the cultural thread in Waikanae |
Completed |
March–June 2018 |
Landscaping and improvements at the Rimu Road/Iver Trask Place intersection |
Completed |
June–November 2017 |
Kāpiti Lights upgrade making the area more pedestrian friendly and helping to create a setting that supports new and existing shops to thrive |
Completed |
August 2016–April 2017 |
Coastlands retail expansion linking Coastlands to the civic precinct and helping to transform Rimu Road into the main street of Paraparaumu |
Completed |
August 2016–January 2017 |
Construction on Kāpiti Road to install a shared pathway and make it easier to get around |
Completed |
August 2016 |
Council briefing on progress |
Completed |
July–August 2016 |
Analysing feedback, summary report of feedback |
Completed |
June 2016 |
Public open sessions held in both Paraparaumu and Waikanae Town Centres |
Completed |
March 2016 |
|
Completed Ongoing |
February 2016 |
Reprogramming of project priorities approved. |
Completed |
December 2015 |
Engaged Design and Construction team led by Brian Perry Civil |
Completed |
June 2015 |
Implementation plan adopted |
Completed |
April/May/June 2015 |
Draft Long Term Plan consultation, deliberations and decisions |
Completed |
March 2015 |
Community open days for Paraparaumu and Waikanae town centres, and for Kāpiti Road |
Completed |
March 2015 |
Cost estimates and programme options developed |
Completed |
January 2015 |
|
Completed |
November 2014 | Assessment of ideas, ranking options and design for Paraparaumu and Waikanae town centres and for Kāpiti Road | Completed |
September 2014 |
|
Completed |
August 2014 | Community open day on draft designs for Waikanae town centre | Completed |
July 2014 | Development of draft design ideas for Waikanae | Completed |
June 2014 | First community open day for Paraparaumu and Kāpiti Road | Completed |
April 2014 |
|
Completed |
A detailed programme for each town centre will be developed.