We're planning Stage 2 of our improvements to Ōtaki Pool. We're aiming to improve pool users’ experience and reduce our carbon footprint and running costs.
These plans are at an early stage, and we haven't yet developed detailed plans. We're looking at a wide range of options, which we'll refine before presenting to Council for a decision.
We're looking at ways to:
- replace or upgrade the existing changing rooms and amenities
- replace or upgrade the ageing pool water plantroom, including installing new filtration and water and treatment systems
- increase the facility’s energy efficiency by replacing the gas heating source with an electric heat pump system
- increase the water and air heating efficiency by including a heat recovery system to reduce energy use and carbon emissions.
Next steps
For our next steps, we'll be:
- Developing a concept design for proposal and associated amenities.
- Engaging with iwi partners, user groups and community for comment on the concept design and functionality.
- Confirming available funding and getting decision to proceed on some or all parts of the project.
- Carrying out design phases – preliminary, developed and detailed.
- Applying for resource and building consents.
- Procurement process – request for proposals and tender, evaluate and award construction contract.
- Construction.
History
Ōtaki Pool is located within Haruātai Park. Stage 1 improvement works to rebuild the pool’s structure were carried out in 2017.
This involved replacing the building’s cladding, strengthening structural steel, installing insulation, installing double-glazed windows and improving heating and ventilation systems.